Transmission Line

icon
2019

connected

icon
52

kilometers

icon
112

towers

icon
2 GW

maximum power

overview

In the Serra Branca cluster (Brazil), Voltalia completes construction of its 2 GW transmission line and plans to anticipate production of its VSM wind projects Voltalia’s new transmission facility in the Serra Branca cluster has reached physical completion.

The new line is capable of servicing wind farms with a total capacity of 2 GW. The line is one of the Continent’s largest construction projects in terms of capacity. 52-kilometer long and sustained by 112 towers, the line is designed for a very high voltage of 500 kV.

Voltalia began developing the line in 2016, progressively securing rights of way over 63 pieces of land with 57 different owners, building permits, interconnection rights and other authorizations.

The process has been swift and smooth thanks to Voltalia’s capacity to team up with the local population, who have benefited from on-site employment and social projects implemented by Voltalia in the region over the past five years.